Culverts are used to drain ditches and to provide stream crossings. We installed a culvert crossing for an intermittent stream with a watershed of 120 ac. Culvert size was determined via Talbot's formula (Walbridge et al. 1984). Costs for this operation are provided in Table 6.

Backhoe transport
$ 50
1 hour backhoe time @ $57/hr
$ 57
20 ft of 36 in. steel pipe @ $20/ft
$ 400
Total
$ 507
TABLE 6. Estimated culvert installation
costs for crossing a 6 foot wide intermittent stream.