Some key stream crossing considerations include stream characteristics, location, purpose, traffic, longevity, cost and design, and construction. Typical expenses and the type of equipment and material required for various crossing options are presented in Table 1:

Type of crossing
Typical costs
Installation consideration
Access limitations
Environmental issues
Appropriate stream
Fords $100 - $1,000 machine, stone limited by high water turbidity low banks, hard bottom, shallow stream
Culverts $200 - $1,500 culvert, equipment, shallow bedrock none storm flow, fish passage small watershed, confined channel
Portable (temporary) skidder bridges $2,000 - $4,000 initial purchase, installation, transport weight limit of bridge drainage from approaches, installation confined stream with higher banks, span less than 25 ft
Simple (permanent) wooden bridges $5,000 - $40,000 design, labor, machine, materials weight limit of bridge possible permit requirement, turbidity during construction small to large
Low-water crossings $10,000 - $50,000 design, location, concrete, pipe, labor, machine none, except during flood stage streambed disturbance during construction, fish passage small to large, shallow stream preferable
Table 1: Decision table for stream crossing options.

 

 

 

 

 

 

 

 

 

 

 

 

In general, the specific location along the stream will be based upon whether or not a ford or elevated structure is desired. The type of stream crossing desired depends on factors such as the overall purpose of the crossing, the amount and weight of traffic, how long the crossing will be used, cost considerations, and design and construction options. For temporary bridges, fixed wooden structures or portable steel or wooden structures are logical choices. For permanent crossings treated wooden bridges or even concrete or steel should be considered. If a bridge is to be designed for public access or unusual conditions then we recommend engaging a professional engineer for the design.